The U.S. Navy’s Columbia-class ballistic missile submarine program is pushing toward a first delivery that the service now expects between October 2028 and February 2029, roughly 12 to 16 months ...
General Dynamics Electric Boat, the Connecticut subsidiary of Reston-based Fortune 500 defense contractor General Dynamics, has been awarded a $2.28 billion contract modification from the U.S. Navy ...
Add Yahoo as a preferred source to see more of our stories on Google. An undated photo of the completed bow module for the future USS District of Columbia at the HII Newport News Shipbuilding plant in ...
Bipartisan lawmakers press the Navy to finalize $100B Virginia & Columbia submarine contracts to protect suppliers and boost ...
The USS District of Columbia, the first Columbia-class vessel, was originally slated for completion in 2027—but that timeline was pushed back one year following construction delays. Five years ago, ...